Feasibility Study of New Airport Road in Capital of Namibia
Time:Jan 28,2021Hits:Hits:-

2015.6~2017.9

The road starts from the west side, 5.2 km away to the Dordabis Interchange, ends at the junction of road B6 and Hosea - Kutako International Airport. The new road runs along the south side of road B6. It's basically east-west and parallel to the road B6. The total length is 21.3 km. This road follows the standard of trunk road, two-way four-lanes, reserved two future lanes in the median, the design speed of 120 km/h, the width of the road is 48.4 meters. Three grade separations (229.2 m long) were designed in this project.