The bridge is located on national highway G234. The bridge is 10769 meters long, 2×16.56 meters wide, designed according to two-way six-lane A-class highway standard.
Span layout:
3×(5×30m) Pre-stressed concrete simple supported and continuously box beams +(65m+110+65) Pre-stressed concrete continuously box beams + 3×(3×50m)+17×(4×50m)Pre-stressed concrete simple supported and continuous T-beams + 5× (80m + 5×120 m + 80 m) pre-stressed concrete continuous box beams + 10× (4×50 m) + 2× (3×50 m) Pre-stressed concrete simple supported and continuously T-beams.
The total investment of the project is about 3.65 billion CNY, of which the total investment of the Yellow River Bridge is 1.988 billion CNY. (Scheduled completed in June 2021).